Ashland Circle Bulkhead Replacement


Click here for more images

 

Project Description: Approximately 100 feet of bulkhead at the southern end of Ashland Circle will be replaced. The bulkhead, including a portion located on Hampton Roads Sanitation District property, will be raised 1.5-2 feet above the existing bulkhead. Additional work includes installing new wrought iron fencing, replacing sidewalk and curbing, replacing asphalt pavement,and installing a concrete storm pipe and landscaping.

Project Status: Construction

Project Cost: $440,000

Completion Date: Summer 2012

Project Manager: Wayne Webster

Neighborhoods Affected: Lafayette, Winona

Location: Ashland Circle