Fort Norfolk - Southampton Ave


The detour route has changed.

Click here to view a detour map

 

Project Description: This project consists of widening portions of Southampton Ave, new sidewalks, curbs and gutters, storm water drainage improvements with an outfall relocation, undergrounding of electrical and telecommunications, water and sanitary sewer system upgrades and signalization of the Southampton and Colley Aves intersection. Additional sanitary sewer improvements will be installed along the 100 block of Colley Ave and water main upgrades along Gresham Dr, north from Brambleton Ave.

Project Status: Construction

Project Cost:$4,500,000

Completion Date: Spring 2012

Project Manager: Chris Chambers

Neighborhoods Affected: Medical Center

Location: 800 block Southampton Ave

Traffic Notes: Southampton will be open to westbound traffic only. Signs will direct drivers to alternate routes.

Planning Districts Design Architect/Engineer Construction Contractor Sponsoring Department/Contact

Medical Center

URS

Kevcor Contracting Corp.

Public Works

 


Director of Public Works
John M. Keifer, PE
(757) 664-4614
Contact by Email

City Departments