Northampton Boulevard Roadway Modifications to Support Lake Wright East


 

 

Project Description: This project will include roadway modifications to Northampton Boulevard and a new traffic signal to support the Lake Wright East development project. Modifications to interstate access is included.

Project Status: Construction

Project Cost: $1,000,000

Completion Date: Summer 2012

Project Manager: Heather Robinson

Neighborhoods Affected: Lake Taylor

Location: Northampton Boulevard at Lake Wright East

 