| THE CITY OF NORFOLK MODIFICATIONS TO HRPDC REGIONAL STANDARDS, 3rd Edition Amendment 1 | |||||||||
| Section | Sub-Section | Name | Add/ Delete |
Modification | |||||
| All Sections | Measurement for Payment. | Replace | See Section 110 for City of Norfolk Department of Utilities Payment Item Descriptions. Replace all references to Mesaurement for Payment in the technical specifications with Section 110. | ||||||
| 102 | VII | Standard Bid Items and Units | Delete | Use City of Norfolk Measurement and Payment descriptions. Refer to Section 110 - Special Provisions. | |||||
| All 100 sections | General Provisions | Replace | Revise all HRPDC General Provisions with Norfolk City Modifications and Department of Utilities Modifications | ||||||
| 200 | II.2.1 | Quality Assurance | Modify | Change the VDOT Road and Bridge Specifications edition date from 1994 to 2002. | |||||
| II.2.2 | Quality Assurance | Add | International Plumbing Code Norfolk Arboricultural Specifications and Standard Practice Manual | ||||||
| III.3.6 | Submittals | Add | Add the following sentences: “The Contractor shall also certify that this substitution will not adversely affect other elements of the Work or the construction schedule, and shall identify local maintenance service and source(s) of replacement parts and materials. Requests for substitutions shall be submitted at the pre-construction meeting and must be approved in writing by the Engineer prior to the start of any construction.” | ||||||
| IV.4.3.B | Aggregate | Modify | Correct the sentence to read, “Aggregates placed directly on the ground for stockpiling purposes, shall not be removed from those stockpiles within 1 foot of the ground until final cleanup. (Only clean aggregate shall be used.) | ||||||
| V.5.1.E | Aggregate | Add | Insert “of this document” after “Division 8 activities” and before the comma. | ||||||
| V.5.10.A.9 | Ductile Iron Pipe | Add | Ductile Iron pipe shall have Sewpercoat calcium aluminate lining, Protecto 401 ceramic epoxy lining, or equal hydrogen sulfide resistant lining approved by the Department. | ||||||
| V.5.10.A.9 | Ductile Iron Pipe | Delete | "or, a polyurethane lining of 35 mils minimum thickness." | ||||||
| V.10.B.5 | PVC Pipe | Modify | Correct the second sentence to read: “When Compact fittings are used, they shall have a minimum acceptable pressure rating of 350 psi.” | ||||||
| V.10.B.7. | PVC Pipe | Modify | Correct the sentence to read: “Solvent cement for non-gasketed PVC pipe shall meet the requirement of ASTM D-2564.” | ||||||
| V. 5.10.C. | HDPE Pipe | Add | HDPE pipe may only be used with prior written approval by the Department. | ||||||
| V.5.10.D.1.a. | Valves | Add | All gate valves for sewer shall open left (counterclockwise). | ||||||
| V.5.10.D.1.c. | Valves | Delete | Delete “with threaded connections” from the first sentence. | ||||||
| V.5.10.D.1.d. | Valves | Add | Accessories: Provide zinc plated bonnet bolts, studs and nuts for unsubmerged service. Provide stainless bonnet bolts, studs and nuts for submerged service. Make wedging devices bronze to iron or bronze to bronze. Provide glands which are bronze or bronze bushed and bronze gland bolts and nuts. | ||||||
| V.5.10.D.3 | Valve Operators | Delete | “A valve key wrench of adequate length and of each type required shall be provided for each project.” | ||||||
| V.5.10.D.4. | Valve Stem Extensions | Delete | Strike out section | ||||||
| V.5.10.D.4. | Check Valves | Add | Provide single disc swing check valves designed to allow a full diameter passage and to operate with a minimum loss of pressure. Provide 1/8 through 3 inch check valves that meet the requirements of MSS SP-80. Provide 4 inch through 24 inch check valves that meet the requirements of AWWA C508. Equip check valves with bronze renewable seat rings, bronze discs or disc rings and bronze disc hinge bushings and pins. Carefully mount discs and provide discs that swivel in disc hinges. Provide pins, discs and other parts that are noncorrosive, nonsticking and properly cured to operate satisfactorily within a temperature range of 34 to 100 degrees Farenheit and with the fluids specified. Equip 6 inch and larger check valves with outside levers and weights. Provide check valves manufactured by American Flow Control, Clow Valve, M&H Valve, Mueller Valve, or approved equal. | ||||||
| V.5.10.F.2.a. | Joint Restraint Devices | Modify | Re-title the section “Pipe Restraint:” | ||||||
| V.5.10.F.2.c. | Joint Restraint Devices | Add | Harnessing: For ductile-iron pipe and fittings with mechanical joints that require harnessing, provide ductile-iron mechanical joint retainer glands. | ||||||
| V.5.10.F.3.c | Joint Restraint Devices | Add | Harnessing: For PVC joints requiring harnessing, provide Series 1300/1390 restraining fittings as manufactured by Uni-flange, Corp., Series 1110 HV and Series 2000 PV as manufactured by EBAA Iron Sales, Inc., or equal. | ||||||
| V.5.11.A.6 | Ductile Iron Pipe Fittings | Modify | Correct the second sentence to read: “When Compact fittings are used, they shall have a minimum acceptable pressure rating of 350 psi.” | ||||||
| V.5.11.A.8 | Ductile Iron Pipe Fittings | Add | After ANSI/AWWA add “Current department approved linings include Sewpercoat calcium aluminate lining and Protecto 401 ceramic epoxy lining. Other hydrogen sulfide resistant linings shall be submitted for review and approval as equal”. | ||||||
| V.5.11.B.5. | PVC Pipe | Delete | "SDR 23.5 or" | ||||||
| V.5.11.B.8 | PVC Pipe Fittings | Add | Add paragraph “For Mains installed, where cover is 10’ (ten feet) or greater, the pipe shall be C900/C905 DR 18 or Ductile Iron.” | ||||||
| V.5.11.B.9 | PVC Pipe Fittings | Add | Add paragraph “All fittings shall be molded or ductile iron. No fabricated fittings will be allowed.” | ||||||
| V.5.11.C. | ABS or PVC Composite Pipe and Fittings | Delete | Strike out section | ||||||
| V.5.11.D.5 | Manholes | Delete | Last sentence that starts with, "Aluminum steps…". | ||||||
| V.5.19.A.6 | Ductile Iron Pipe fittings | Modify | Correct the second sentence to read: " When Compact fittings are used, they shall have a minimum acceptable pressure rating of 350 psi." | ||||||
| V.5.19.B.3. | PVC Pipe | Delete | “couplings, and fabricated fittings” and “or fitting”. | ||||||
| V.5.19.B.6 | PVC Pipe | Add | Add as the final sentence in the paragraph: "Where Schedule 80 PVC is used, solvent cement shall meet the requirement of ASTM D-2564." | ||||||
| V.5.19.B.7. | PVC Pipe | Delete | Strike out paragraph | ||||||
| V.5.19.C. | Copper Water Pipe | Delete | Strike the sentence that starts, “Fittings shall be wrought…” | ||||||
| V.5.19.D.1.b. | Valves | Add | All gate valves for water shall open right (clockwise). | ||||||
| V.5.19.D.1.c. | Valves | Delete | Strike out “with threaded connections”. | ||||||
| V.5.19.D.2.a | Butterfly Valves | Modify | Replace “16 inches” with “20 inches”. | ||||||
| V.5.19.D.4. | Valve Operators | Modify | Strike out the sentence that begins, “A valve key wrench…” Add the following: “NOTE: Water valves open right (clockwise).” | ||||||
| V.5.19.D.5. | Valve Stem Extensions | Delete | Strike out paragraph | ||||||
| V.5.19.F.1 | Fire Hydrants | Add | "All fire hydrants shall be manufactured in complete accordance with American Water Works Association Specification C502, latest revised edition, and shall be as manufactured by the Darling Valve & Manufacturing Company (Model B-50-B), Mueller Centurian A-421, Pacer Model W-67, Kennedy K-81, or approved equal. Hydrants shall have full 360 degree revolving heads and shall open by turning the operating nut to the right (clockwise). | ||||||
| V.5.19.F.2. | Fire Hydrants | Delete | "The fire hydrant shall be painted with a high gloss, alkalyd industrial enamel (colors to be selected by Owner)". | ||||||
| V.5.19.F.3 | Fire Hydrants | Delete | Strike out paragraph | ||||||
| V.5.19.F.5 | Fire Hydrants | Modify | Change the the section on steamer nozzles from, "…nozzle with 4-inch (or 4 1/2-inch as specified by the Owner) National…" to, "…nozzle with 4 1/2-inch National…". | ||||||
| V.5.19.F.6 | Fire Hydrants | Delete | Strike out paragraph | ||||||
| V.5.19.H.1 | Water Meters | Delete | “meter yoke”. | ||||||
| V.5.19.H.2 | Water Meters | Delete | “and installed” | ||||||
| V.5.19.I.4.a. | Concrete Reaction Blocking | Add | The phrase, ", or as designated by the Engineer," after the word, "Drawings". | ||||||
| V.5.19.I.4 | Concrete Reaction Blocking | Delete | subsections b and c | ||||||
| V.5.19.J.2. | Tapping Valves and Sleeves | Delete | Strike out the sentence, “The valves shall be subjected to a factory test…” | ||||||
| V.5.19.J.3.a. | Tapping Sleeves for DI Pipe and PVC C-900 | Modify | In the first sentence insert “full bodied” between “shall be” and “mechanical joint”. Delete “in accordance with ANSI/AWWA C110/A21.10. and” from the sentence beginning with “Tapping sleeves shall be…” | ||||||
| V.5.19.J.3.b. | PVC pipe (Other than C-900) | Delete | Strike out the first paragraph, which begins, “Tapping sleeves shall be complete…” | ||||||
| V.5.20.B. | Subsurface Utility Warning Tape | Modify | Replace “metalized” with “non-metallic”. | ||||||
| V.5.21.F.1 | Manhole Rehabilitation Using Cementious Products | Delete | Delete entire section | ||||||
| V.5.21.I.2 | Manholke Frame Seals | Delete | After "only be installed with the" delete "cementious lining and" | ||||||
| 303 | II.2.2.B.5 | Trenching, Backfilling, and Compaction | Modify | Re-write the last sentence to read ”In such instances, sheeting will be cut off at least two (2) feet below finished grade and left in place.” | |||||
| II.2.2.E.1 | Trench Bedding and Backfilling | Modify | Replace “Contractor” with “Inspector”. | ||||||
| II.2.2.E.4. | Trench Bedding and Backfilling | Modify | Replace the paragraph with: “Backfill material shall be solidly compacted around the pipe in 6” layers up to sub-base of the roadway or the existing ground elevation. As a minimum, compact each layer of the backfill material to 95% maximum density as determined in accordance with VTM-1. | ||||||
| II.2.2.E.7. | Trench Bedding and Backfilling | Modify | Replace in the first sentence, "...material to not less than the following percentages at the maximum…" with "…material to 95% maximum…". | ||||||
| II.2.2.E.7. | Trench Bedding and Backfilling | Delete | sub sections “a – c”. | ||||||
| II.2.2.E.7.d. | Trench Bedding and Backfilling | Add | “The City may, at any time, require compaction testing to ensure compliance with the specifications. A recognized testing laboratory that is selected by the City will conduct all tests. The testing laboratory is to be qualified in the field of the materials to be tested. If applicable, all tests will be conducted in accordance with V.D.O.T.’S “Manual for Virginia Testing Methods” (Current Edition, as Revised). Payment for all tests will be in accordance with the following: A) The cost of all tests failing to meet the minimum requirements will be borne by the Contractor. B) The costs of all tests that either meet or exceed the minimum requirements shall be borne by the City. | ||||||
| II.2.2.F. | Restoration - General | Delete | “in accordance with the drawings and at a minimum the areas disturbed shall be”. Leave the remainder of the sentence. | ||||||
| II.2.2.G.2. | Pavement Removal for Placement of Pipelines | Modify | Replace the sentence beginning, “The minimum requirements for a…” with, “Temporary pavement shall be of minimum 6” stone with 3” of cold mix laid to the original line and grade and thoroughly compacted.” | ||||||
| II.2.3. | Tolerances | Delete | Complete Section | ||||||
| 801 | II.2.2.C.7. | Pipe Installation | Modify | Replace “300” with “100” | |||||
| II.2.2.F. | Tracer Wire | Modify | Replace “attached every 10 feet to” with “1 foot above”. | ||||||
| II.2.2.G. | Subsurface Utility Tape | Modify | Re-write the paragraph to read,” All non-metallic water mains shall be identified by a subsurface non-metallic utility warning tape placed at an elevation of 12” above the copper tracer wire or as directed by the owner, conforming to Section 200.” | ||||||
| II.2.3.A. | Valve Installation | Modify | After “direction of openings” insert the following, “(All water valves open right)”. Re-write the second sentence to read, ”Valves found not opening to the right, or determined to be defective by the Owner shall be rejected, removed from the site, and replaced by the Contractor at no additional cost to the Owner.” | ||||||
| II.2.6.C. | Restraint | Add | After “…coating” add the following, “or as directed by the Owner.” | ||||||
| II.2.7.B. | Connections to Existing Mains | Delete | Delete the sentence that begins with, “Connection shall be…”. Delete the last two sentences and replace with, “The Owner shall make every effort to have a complete shut down. Failure by the Owner to achieve a complete shut down shall not entitle the Contractor to any additional compensation.” | ||||||
| II.2.7.B.4 | Connections to Existing Mains | Modify | Replace the paragraph with, "Tie-ins to existing mains shall only be performed after the new main has been satisfactorily pressure tested and chlorinated. The contractor may not tie-in the new main to the existing main until after the results of the bacteriological tests have been completed and approved by the owner." | ||||||
| II.2.7.C. | Tapping Existing Mains Under Pressure | Delete | Delete subsections 2, 3, and 5. | ||||||
| II.2.7.C.4. | Tapping Existing Mains Under Pressure | Modify | Change the pressure to 150 psig and maintain the pressure for 1-hour. | ||||||
| II.2.7.C.6. | Tapping Existing Mains Under Pressure | Add | In the first sentence, after “…branch are acceptable” add the following, “unless otherwise directed by the Owner.” | ||||||
| II.2.8.B.1. | Pressure Test | Modify | In the sentence which begins, “Water mains shall be…” remove the portion that states, “1.5 times the expected working pressure or” and the portion that states, “whichever is greater”. In the sentence which begins, “The pressure test shall be…” after “that are discovered”, insert, “during and”. After “…replaced by the Contractor” insert “and retested.” | ||||||
| II.2.8.B.3. | Pressure Test | Add | “, or as directed by the Owner.” | ||||||
| II.2.8.B.8. | Pressure Test | Modify | Replace this subsection with, “The test pressure shall be maintained at the pressure stated in the project specifications throughout the duration of the test period. The water used to maintain the test pressure shall be measured and shall be less than the allowable leakage in order for the main to have passed the test.” | ||||||
| II.2.8.B.10. | Pressure Test | Modify | After “…restraint and support” insert “ for testing apparatus”. | ||||||
| II.2.8.C.2. | Leakage Test | Modify | Insert the word “excess” between “…until the” and “leakage is eliminated.” | ||||||
| 802 | I.1.1 | Description of Work | Delete | …"up to 18-inch in diameter." | |||||
| I.1.2.B.5. | Submittals | Modify | Replace "3 years" with "1 year from date of final acceptance". | ||||||
| II.2.1.E. | General | Add | Provide cut sheets for all manholes, 100 ft. stations and end-of-line cleanouts. | ||||||
| II.2.1.F. | General | Add | All Services which are reconnected to the replaced sewer main shall be shown on the "As Built" drawings with the exact distance from the nearest manhole and with the details of the method of reconnection. | ||||||
| II.2.2.C.4. | Pipe Laying | Add | "If a swab is in the pipe for cleaning, the grade shall be checked and recoreded for each joint of pipe. | ||||||
| II.2.2.C.6 | Pipe Laying | Modify | After"…shall be close" insert " by use of a temporary bulkhead" and delete " to the satisfaction of the Owner". | ||||||
| II.2.2.D.1. | Alignment and Grade | Modify | Replace "Drawings" with "approved laying schedule". | ||||||
| II.2.2.D.2. | Alignment and Grade | Delete | Entire subsection | ||||||
| II.2.3.B. | Manhole Installation | Add | To the end of the second sentence after: non-shrink grout-"and goated to match surfaces of manholes." | ||||||
| II.2.4.A.1. | Testing and Inspection | Delete | The word "flushing". | ||||||
| II.2.4.A.2. | Testing and Inspection | Modify | Change the sentence to read, "The Contractor shall submit to the Owner, at least 48 hours in advance, any requests to schedule testing and inspection." | ||||||
| II.2.4.A.6. | Testing and Inspection | Add | Sub-section 6 to read, "Contractor is responsible for repairing any deficient work at no additional cost to the Owner." | ||||||
| II.2.4.B.1.a. (5). | Pipe Testing - Gravity Lines | Add | "Contractor is responsible for uncovering and restoring spot check sites at no additional cost to the Owner." | ||||||
| II.2.4.B.1.a. (6). | Pipe Testing - Gravity Lines | Modify | Replace the word, “tha” with “the”. | ||||||
| II.2.4.B.1.a. (8) | Pipe Testing - Gravity Lines | Modify | Replace the last sentence with, "See Section 811." | ||||||
| II.2.4.B.1.b | Pipe Testing - Gravity Lines | Add | Insert "Contractor is responsible for removal of mandrel if it becomes stuck in the pipe." before the sentence that begins with "Any sections that…" | ||||||
| II.2.4.B.1.d | Pipe Testing - Gravity Lines | Add | "A log of comments made on the video tape shall be supplied with the associated pipe footage shown." | ||||||
| 803 | II.2.2.E | Tracer Wire | Modify | Replace "attached every 10 feet to" with " 1 foot above". | |||||
| II.2.2.F | Subsurface Utility Tape | Modify | Re-write the paragraph to read "All non-metallic water mains shall be identified by a subsurface non-metallic utility warning tape placed at an elevation of 12" above the copper tracer wire or as directed by the Owner, conforming to Section 200." | ||||||
| II.2.3.A | Valve Installation | Modify | After "direction of openings" insert the following; "(All sanitary sewer valves open left)". Re-write the second sentence to read "Valves found not opening to the left, or determined to be defective by the Owner shall be rejected, removed from the site, and replaced by the Contractor at no additional cost to the Owner." | ||||||
| 804 | II.2.2.C.3 | Jacking | Add | The thrust wall and jacking system shall be designed to carry the thrust of the jacks to the soil without excessive soil deflection and in such a manner as to avoid any disturbance of adjacent structures or utilities. | |||||
| II.2.2.E.4. | Carrier Pipe Installation | Add | The carrier pipe shall be electrically isolated from the casing pipe. | ||||||
| 805 | I.1.2.B.2 | Unusual Conditions | Modify | Replace the second half of the sentence that begins, “pressure tested in place…” and ends “…and tested in place.” with, “, and meets current Virginia Department of Health Sewage Collection and Treatment Regulations.” | |||||
| 810 | II.2.2.F.3 | Acceptance of Cleaning Operation | Add | A television inspection shall be completed after cleaning to verify that the cleaning operation was successful. The television inspection shall be in accordance with Section 811 - Television Inspection. | |||||
| 811 | I.1.2.A. | Submittals | Add | "Video Tapes shall be Extra High Grade T-120 VHS videotape for all television surveys. All taping shall be performed as SP (Standard Play, 2hrs/tape). All video shall be submitted to the Owner and will become the property of the Owner. Two labels are requried, with one label placed on the video and the other on the container. Permanently label each video with the following information: Owner Name, Contractor Name, Tape No., Date Televised, Date Submitted, Project Name, Branch Name, Street Name; Manhole No. From, Manhole No. To, Pipe Diameter, Pipe Length, Street Name." | |||||
| I.1.2.D. | Submittals | Add | Overflow Prevention Plan | ||||||
| I.1.2.E. | Submittals | Add | Overflow Containment and Cleanup Plan | ||||||
| II.2.1.B.1. | Equipment | Add | Sewer scanner and evaluation technology, similar to the Blackhawk pipeline assessment system, is an acceptable alternative to CCTV. | ||||||
| II.2.2.A.2. | Flow Control | Modify | The end of the last sentence to read, "…unless approved by the Owner in advance". | ||||||
| 812 | I.1.2.P. | Submittals | Add | Overflow Prevention Plan | |||||
| I.1.2.Q. | Submittals | Add | Overflow Containment and Cleanup Plan | ||||||
| 822 | Replace entire section with Supplemental Specification for Manhole and Wet Well Rehabilitation and Coating. | ||||||||
| Standard Details | RC_02 | Utility Locations | Delete | ||||||
| EW_02 | Payment Limits Trench Excavation and Backfill | Delete | |||||||
| EW_03 | Trench Width Detail for Payment of Contingent Items | Delete | |||||||
| CI_08 | Residential Entrance w/out Curb and Gutter | Delete | Use Norfolk Public Works/Codes Standard Driveway Entrance Detail | ||||||
| WD-01 | Dual Service Connection | Delete | Dual Service connection not allowed. | ||||||
| WD_02 | Water Service Installation Detail | Modify | Replace '7.5" - 22"' with '18".' Replace '36" min.' with '24" min.' Delete Note #1. | ||||||
| WD_04 | Water Meter Box (Type II) | Delete | |||||||
| WD_05 | Blow Off Assembly | Replace | Use the Norfolk Standard Detail for Blow-Off Assembly, C.S.5. | ||||||
| WD_06 | Fire Hydrant Setting (TypeI) | Modify | Hydrant nozzle should be 16" from the face of the curb and 16" above the ground elevation. Delete both references to 12" PVC, C-900 or PVC Truss Pipe" and replace with "6" DI Riser". Delete Note #3. Add the following notes: 5. Use Megalug to connect the hydrant and the 6" DI Pipe. 6. Tie rods to be used from the valve to the tee. 7. Use Norfolk Standard Small Valve Box, C.S. 5A. | ||||||
| WD _07 | Fire Hydrant Setting (Type II) | Delete | |||||||
| WD _08 | Fire Hydrant Setting (Type II) | Delete | |||||||
| WD_09 | Temporary Manifold For Test and Chlorination | Modify | Actual set up may not look exactly like this detail. After detail note "Gage approved…" insert "or furnished". | ||||||
| WS _01 | Standard Valve Box Frame and Cover | Delete | Use the Norfolk Standard Detail for Small Valve Box Frame and Cover, C.S. 5A. | ||||||
| WS _02 | Valve Setting Detail | Modify | Delete "12" PVC, C-900 or PVC Truss Pipe" and replace with "6" or 8" Riser Pipe, material to match main." Delete the requirement for "#57 Stone" above the main to support valve box." Delete the requirement for "36" cover". Remove the requirement for "w/retainer gland." Modify the first sentence in Note #2 to read: "Plastic coated...Tracer wire laid 12" above top of main". Add "non metallic locator tape laid 12" above tracer wire." | ||||||
| WS _03 | Manual Air Vent Assembly | Replace | Use the Norfok Standard Detail, C.S. 5B. | ||||||
| WS _05 | Standard Thrust Blocks | Delete | |||||||
| WS _06 | Obstruction By-Pass Uniform Offset | Delete | |||||||
| SS_01 | Standard Precast Concrete Manhole w/Extended Monolithic Base | Replace | Use Norfolk Standard Detail, C.S.1E. | ||||||
| SS_02 | Precast Concrete Shallow Manhole | Replace | Use Norfolk Standard Detail, C.S. 1F. | ||||||
| SS_04 | Sanitary Sewer Interior Drop Manhole | Replace | Use Norfolk Standard Detail, C.S. 1G. | ||||||
| SS_09 | Sanitary Sewer Manhole Casting (24") | Replace | Use Norfolk Standard Detail, C.S.2 | ||||||
| SS_10 | Sanitary Sewr Manhole Cover (24") | Replace | Use Norfolk Standard Detail, C.S.2 | ||||||
| SS_11 | Saniary Service Lateral Clean Out Frame and Cover | Replace | Use Norfolk Standard Detail, C.S.6. | ||||||
| SS_12 | Sanitary Service Lateral Clean Out Frame and Cover For Heavy Loads | Delete | |||||||
| SS_13 | Sanitary Sewer Main Line Clean Out Box | Replace | Use Norfolk Standard Detail, C.S.3. | ||||||
| SS_14 | Sanitary Sewer Service Connection | Replace | |||||||
| SS_15 | Dual Sanitary Sewer Service Connections | Delete | Dual Service connection not allowed. | ||||||
| SS_16 | Deep Sanitary Sewer Service Connection | Delete | |||||||
| Raw Water | Air Release Vault | Add | |||||||