Jamestown Crescent Culvert Replacement

JamestownCrescentCulvert.jpg
Design Information

Construction Update and Traffic Information

  Project Description: Full replacement of a deteriorated culvert with a new concrete, single barrel box culvert with wingwalls and riprap, pavement resurfacing, water line relocation, and sidewalk, curb and gutter work.

Project Status:  Construction

Project Cost:
  $700,000

Completion Date:  Fall 2013

Project Coordinator:  Christine Atkinson

Neighborhoods Affected:  Larchmont, West Highland Park, Colonial Place

Location:
Jamestown Crescent between Bolling and Magnolia Avenues just north of the Colley Avenue Bridge

Planning Districts Design Architect/Engineer Construction Contractor Sponsoring Department/Contact

Edgewater-Larchmont

Moffatt & Nichol

Quality Enterprises, USA

Public Works