GRANBY STREET BRIDGE REHABILITATION

LOCATION
Lafayette River between E. 42nd Street and Willow Wood Drive (over Lafayette River)

PROJECT INFORMATION
This project will improve the condition of the Granby Street Bridge by repairing key structural components and protecting bridge elements from deterioration.

SCOPE OF WORK
  • New latex modified concrete deck overlay
  • Repair structural components
  • Seal and waterproof bridge
  • Replace new elastometric bearings and expansion joints
  • Reconstruct portions of roadway and sidewalk at bridge approaches

PROJECT STATUS
• Estimated construction start date: Spring 2019
• Estimated construction completion date: Summer 2020

PROJECT COST
6-7 million dollars (98% federally funded)
CONSTRUCTION IMPACTS
  • Lane closures will be required; at least one lane in each direction will be open at all times
  • One of the two existing sidewalks will be open at all times
  • The bike lane over the Granby Street Bridge will be temporarily closed during construction
NEIGHBORHOOD CIVIC LEAGUES
• Riverpoint Civic League
• Colonial Place/Riverview Civic League

               

Department of Public Works 810 Union Street, Suite 700 Norfolk, VA 23510 www.norfolk.gov/granbybridge

Updated March 14, 2019


Contact Us
Project Manager
Paul.Britton
Email
757-664-4605

Construction Manager
Olga Beltsar
Email
757-664-7336

Design Architect/Engineer
Moffatt & Nichol
757-628-8222
Construction Contractor
Pending contract award
Name (TBD)
Number (TBD)


Construction Inspector
Name (TBD)
Number (TBD)


GranbyST Bridge.jpg