Sidewalk Infrastructure-Citywide

Project Location

2 phases, 5 locations for new sidewalk:

Download Project Location Map (PDF)

Project Information

This project will install new 5’-6’ concrete sidewalk at five critical locations throughout the City. Improvements will also include ADA ramps, curb and gutter, drainage improvements, and signage.

Scope of Work

  • 5’ concrete sidewalk
  • Drainage improvements, such as curb and gutter and piping
  • Signage and pavement markings

Project Status

Design

Project Schedule

  • Phase 1
    • Public Engagement: Summer 2020
    • Construction Start: Fall 2021
  • Phase 2 
    • TBD - Dependent on funding

Project Funding

Capital Improvement (0% Federal/State, 100% Local) $899,341 ($0 Federal/State, $899,341 Local)

Construction Impacts

Lane closures will be required but closures will be short and have minimal impact to traffic

Project Documents

Civic Engagement

  • Ward 2 (Councilwoman Doyle)
  • Ward 3 (Councilwoman Johnson)
  • Ward 4 (Councilman Riddick)
  • Ward 5 (Councilman Smigiel)
  • Superward 6 (Councilwoman McClellan)
  • Superward 7 (Councilwoman Royster)